The project of the Alkaline Adaptation process is progressing according to plan and the detailed engineering has reached a completion of 70 %. The procurement of the equipment is almost completed, only a few orders are still to be placed and contractors for installation are under negotiation. The new chemical storage building, built to free up space inside the mill for the installation of the Alkaline Adaptation process equipment, is finished.
The program for measurements and evaluation is ready and will be updated closer to the evaluation trials.